he day has finally come. We have our plan pulled together and its time to bring this car wash from the 1980’s to 2017! We are putting in the most advanced tunnel in CT and can’t wait to share it with you. It’s going to take a few weeks, but we think you are going to be blown away with what this new wash can do!

Some of the highlights:

  • Belanger Spin Lite Tunnel
    Literally the best car wash equipment money can buy
  • Brand New Lobby and waiting area.
  • More Free Vacuums
  • Free Rug Beaters to go with those free vacs
  • An Exterior Refresh!
  • Plus More

Progress:

Waterbury Wash Upgrade

Timeline:

October 4th - Wash Upgrade Begins

If you are an unlimited member, do not stress, this month is on us. Even though you won’t be paying for it, you can still use your plan up at our Prospect Location.

Get Directions

October 5th - Pulling out Old Equipment

Today is the day you’ve all been waiting for. Old equipment is getting pulled out today. We are going to be trying to get this done as fast as possible. In the meantime, you can visit our other location in Prospect, CT.

October 9th - Prepping Tunnel For New Conveyor

New conveyor going in. Good customers know this has been a bane for us this entire year. After 30 years, it’s time for the heart of our wash to become something shiny and new! We also will be improving the turning radius into the tunnel. No more 3 point turns!

October 11th - Getting Busier

Today is a monster day. Old pavement is coming out and being replaced, concrete for repairs in the conveyor is being done, and old windows are going to be removed and replaced! And we are also adding some beautiful landscaping to the front! Take a drive by and see the progress!

October 14th - Lobby/Windows and more

The lobby remodel is getting there. All the old windows looking into the wash have been replaced. Fresh paint is in and floors are going to be installed on Monday. Our equipment delivery for the tunnel is coming at the start of the week and then we have a bit of time to get everything wired up and running again. It’s a slow process, but it will be worth it!

October 16th - Equipment Delivered

The trucks are here! Two trailer loads of new equipment! Finally starting to see the light at the end of the tunnel (Pun Intended). Once delivery is done, we will start standing the equipment up. We are finally over the hump!

October 18th - First course of paving and floors

The first course of paving is being installed today, the lobby floors are going in, and the conveyor is being welded in. Starting to finally take form!

October 26th - Final Coat of Paving

The final coat of paving is going in and it looks great!

Nov. 2nd - Lobby and Lights

The lobby is mostly done and we are starting to turn on some of the equipment and lights in the tunnel. Down to the final days.